Park Street Intersections

18BPS13

This project includes realigning the intersections at Emma/Berry/Park and Park/Caudle/Powell. The Emma/Berry/Park intersection will align Berry and Park into one intersection, and the Park/Caudle/Powell intersection will be replaced with a wide, one lane roundabout. These improvements will include extending Emma Street's textured sidewalk through the Emma/Park/Berry intersection and include a greenway crossing through the Park/Caudle/Powell roundabout.  

  1. STATUS
  2. CONTRACTORS
Phase Details Phase Est. Completion
*All Dates Subject to Change*
Design 100% Complete June 2020
Right-of-Way Acquisition 100% Complete February 2021
Utility Relocation 100% Complete Spring 2021
Construction Pending August 2022