40th Street 

18BPS4

This project includes widening 40th Street as a three-lane road with a center turn lane from Falcon Road north to the Spring Creek bridge. This project will aslo include sidewalk and a 12 foot sidepath with mid-block pedestrian refuge islands.

  1. Status
  2. Contractors
Phase Details Phase Est. Completion
*All Dates Subject to Change*
Design 100% Complete April 2019
Right-of-Way Acquisition 100% Complete  April 2021
Utility Relocation  Pending June 2022
Construction Pending August 2023