Home

Posted on: June 2, 2016

East Emma Ave. improvement project

Emma Ave. Improvement

Update - Feb. 9, 2017


At the January 10 City Council Meeting, the Council approved a resolution for Springdale Water Utilities to award the construction contract for the streetscape improvements to Crossland Heavy Contractors in the amount of $1.164 million. Crossland has a notice to proceed date of February 20, and the streetscape project is scheduled to be complete by Aug. 15, 2017, weather permitting.


Update - Jan. 9, 2017


Work on the sewer lines is complete, and crews are working on the water lines, which should be complete by early February, weather permitting.


The final phase of the project will be improving the streetscape. The streetscape project will extend essentially from Hewitt Street to Berry Street. The portion from Water Street to Berry Street will include milling, curb reconstruction in places, sidewalk work on the north side of the street, and an overlay.


The section from Hewitt Street to Water Street will include undercutting (i.e., complete street reconstruction), curb reconstruction, and complete sidewalk replacement. 

   

Included in the project will be landscaping, irrigation, street lighting, and other amenities such as benches and trash cans.


Currently the streetscape project is scheduled to be complete in late summer 2017.


Update - Oct. 7, 2016

Currently, Springdale Water Utilities is working on a three-part project to improve the water and sewer lines and the streetscape on Emma Ave.


Work on the sewer lines will be done in December and crews will begin to work on the water lines, which should be complete by early February, weather permitting.


The final phase of the project will be improving the streetscape, including restriping the road and crosswalks, doing curb and gutter repairs and putting in trees and shrubbery. Weather permitting, the final phase should be complete by late spring, early summer 2017.


Original release - June 2, 2016


Springdale Water Utilities has begun work on East Emma Ave. to replace all sewer services and reline the sewer line from Willella Pl. to the A&M Railroad tracks. This project will be completed by Brothers Construction, and their contract is for 150 days.


In order to complete this project, crews will have to block the road and re-route traffic at various times. There are two message boards, one by Jones Center and one by the railroad tracks, informing oncoming traffic of road closures when necessary.


These upgrades will improve the sewer services to the homes and buildings along East Emma Ave.


Facebook Twitter Google Plus Email